Control Room Case Study

Background:

When planning the location of their new control room, this major utilities provider selected a centralised CBD location, within an existing multi-storey building on a busy street.

Due to this new site being the ‘central nerve centre’ for the company, it was imperative that reliable permanent power was always accessible to support services.

Problem:

  • The generator required installation within an existing building, in a busy location – with minimal disruption to the project site and surrounding areas.

Solution:

  • The Power Generator Systems team strategised a retrofit to this existing multi-storey building, of a Kohler generator to support their new centralised control room
  • PGS co-ordinated a multi-faceted crane lift for the machine & other items, then negotiated its manoeuvre into an existing plant room, 14 storeys up
  • We added exhaust and ventilation facilities, to support generator operations when in use

Outcome:

  • The company are now situated in their new CBD location, within a high-rise that has been retrofitted by PGS, to better support services, backed by continuous emergency power

 

Contact Us

Contact Us Now
Subscribe to our email newsletter to receive the latest news and updates
  • This field is for validation purposes and should be left unchanged.